Bladt completes Hornsea One helideck.

Courtesy of Bladt.

Bladt has confirmed the completed installation of a helideck on the first out of three substation topsides, for Hornsea Project One.

The weight of each individual substation will be 2,800 tons. Bladt Industries is responsible for the construction of steel structures for all three substations. They have confirmed it is the first time Bladt signed a contract for three substation topsides at the same time.

Hornsea One is being developed by DONG Energy as the first of three stages of what is expected to be the world’s largest wind farm. It is located approximately 120 kilometres off the coast of Yorkshire in Great Britain.

Earlier this month, DONG Energy won the CfD auction for the construction of Hornsea Two.

 