Strategic project brings Moldova closer to integration with the European electricity network
Work on the Vulcănești–Chișinău Energy Independence Line (400 kV) has reached another milestone: 87% of construction is complete and 97 km of cables have already been installed. Teams are working in parallel at both the Chișinău and Vulcănești substations to finish equipment installation and commissioning. The new 157 km overhead transmission route will include more than 500 towers and…